Falmouth Residents: Take the Turbines Down [Video]
Nearly one hundred Falmouth residents attended a Board of Selectmen meeting last night to peacefully protest and speak out against the ongoing operation of three identical industrial wind turbines in the Falmouth Industrial Park, pleading with selectmen t
The public was invited to provide comments at Wednesday night’s meeting in Town Hall related to various options that will be presented to voters at town meeting this spring.
Prior to the meeting, dozens of residents held a candle light vigil and prayed that the selectmen would not only hear their voices, but also take immediate action to stop what they described as a nuisance and danger to their health.
Nearly 50 residents voiced their opinion during the public comment session, with almost every comment opposing the future operation of the turbines.
Eric Sockol’s home at 819 Falmouth Highway is just 1,000 feet from Wind 2, a town-owned industrial wind turbine. Sockol passionately urged selectmen to remove the turbines immediately. He said Falmouth has an obligation to protect the health of its citizens, despite any economic consequences that may come from tearing down the turbines.
“Understand there are some issues that are more important than simply economics,” Sockol said.
Richard Bowen’s home also neighbors one of the town-owned turbines. Bowen said that the town had somehow made a great error by installing the turbines and feels town officials are not willing to own up to the mistake. Bowen also urged selectmen to take the turbines down.
“Do the right thing, please, for our sake,” Bowen said.
John Ford, a resident living on Blacksmith Shop Rd., said neighbors of Wind 1 and Wind 2 have lost peace and quiet and good health. Ford suggested using solar panels as an alternative to wind power.
“I request that you join your fellow residents and neighbors and decide to remove the wind turbines and replace them with people friendly photovoltaic arrays,” Ford said.
Judy Fenwick does not live near the turbines, but she was a member of the working group that was organized by the town to develop options for dealing with the wind turbines. Fenwick told selectmen that after much deliberation she believes that the health of Falmouth residents should be placed above any financial repercussions of removing the turbines.
“I ask that you don’t be counter dependent and that you ask the state for help before you ask the Falmouth taxpayers,” Fenwick urged.
Residents who were unable to make Wednesday night’s meeting can still submit a statement to the Selectmen’s Office by 4:30 p.m. Monday January 28th. Statements can also be emailed to townmanager@falmouthma.org by the deadline.
Bill Carson
8:01 am on Thursday, January 24, 2013
There is virtually no benefit to justify the harm caused to victims. Even if such benefits existed, they could hardly outweigh the harm being done to people. If we continue to blame the victims and deny this truth, we will soon become victims of our own devices.
This last thought is cold comfort to those who must face the steady erosion of their health, their families’ and financial reserves, and the destruction of their very livelihoods that is created by living too close to turbines.
The victims of Big Wind are like so many canaries in the mine shaft, who flee or fall in the face of this industrial toxin. Those who blame them are like unwitting miners who stand staring dumbfounded at the obvious, wondering what these canaries have done to bring this catastrophe upon themselves—and then continue along their merry way down the mine shaft, oblivious to the clear and present danger as though they are immune to it. Until it is too late.
mark cool
9:21 am on Thursday, January 24, 2013
There was a suggestion made that this problem be fixed with the Constitutional power of eminent domain. In effect, to buy out or take surrounding properties of those owners claiming to be aggrieved by the turbines.
For any governmental body to consider this action “reasonable”, the establishment of “benefit” or “community good” must be realized.
Secondly, the action would be precedent setting. The result of which would foster repercussions impacting the similarly sized, privately owned Webb turbine in the Falmouth Technology Park. That turbine seems the next to have a ‘bulls-eye’ painted on it’s placement.
Speaking to the “benefit”, the fiscal municipal benefit is absurd (no matter the ‘spin’). Mr. Suso (town mgr), in his proposed budget to the Finance Committee, spoke of FY 2014 (2015?) projections based upon a “sustainable model” involving 24/7 turbine operations. Mr. Suso’s budget proposal, given the “purchasing of home” contingency portion of one of the options, as well as now with this power of eminent domain suggestion, DOES NOT include any costs associated with the purchasing of homes. Odd?
During the WTOP ball park estimates for the endeavor were in the range of $9 -$16 million. The profit flow tabulations, from the WTOP report, forecasted a positive flow only at the end of the turbine’s viable operational lifespan. Those numbers were marginal at best.
mark cool
9:21 am on Thursday, January 24, 2013
The benefits of achieving climate action targets are controversial. The WTOP avoided this debate like the plague. Similarly, the process set the ground rule allowing claims (i.e. health and climate impact) to be treated as reality. The climate benefit argument is a stretch, but is certainly more viable than the municipal financial benefit.
The speaker also suggested a benefit comparison over looked so far. That being to replace existing turbines with a “task orientated” wind system, compliant with the new bylaw being proposed by the planning board. The original project’s 660Kw machine was to serve all the waste water plant’s electricity needs. Such a turbine scale seems far more appropriate for the site, as well as having been likely to make all involved happier than we are today.
Willis Montgomery III
9:32 am on Thursday, January 24, 2013
Please don't take the turbines down. Keep them spinning.
Bill Carson
10:09 am on Thursday, January 24, 2013
There are residents who say keep the wind turbines spinning. The simple facts are the turbines cause health problems .The Town Meeting members dislike the wind turbine abutters so much and they think that they are better than the abutters. Town Meeting members voted to keep the turbines spinning despite the health of a hundred homes.
An economic down turn and unemployment has heightened existing class and political differences in Falmouth over the placement of wind turbines in residential locations. Cash vs Health !
Did you ever ask yourself what the general public of Germany was thinking of during World War II ? If you lived in Germany during those times wouldn't you wonder what happened to your neighbors?
What happened to all the people in Germany in World War II ?The answer to this is that most Germans say they were unaware of what happened to those that were no longer to be seen on the streets anymore.
The residents of Falmouth are well aware of three years of noise complaints who describe the noise as torture. The people of Falmouth through a democratic process continue the torture on the abutters of the turbine .
mark cool
10:33 am on Thursday, January 24, 2013
"For decades, big tobacco successfully suppressed the inconvenient truth that smoking harms people’s health. The wind development industry closely follows big tobacco’s deception playbook — taking advantage of people’s best intentions to protect our environment as they desperately cling to outdated and inaccurate studies." ~ Steve Deslauriers ~ Green Bay Press Gazetts
Bill Carson
10:55 am on Thursday, January 24, 2013
Falmouth is looking at economic feasibility with the Vestas V 82 gear driven turbine. The turbine a political embarrassment to the Massachusetts Technology Laboratory was sold to the Town of Falmouth with an advance of one million in RECs Renewable Energy Credits from the MTC. The turbine was housed in a warehouse in Texas for five years at $3500.00 per month. The MTC now known as the Mass CEC couldn't even auction the turbine in 2009.
The Town Meeting Members need to do their own research on why no one would buy the turbine. The problem in operation and maintenance of these type of turbines. In the past few months three turbines installed three years ago have catastrophic failures . Otis ANG Base ,Cape Cod - Princeton ,Massachusetts and Portsmouth High School ,Rhode Island
Falmouth Wind 1 shut down over an electric switch condensation problem at Thanksgiving .The turbine is at its three year birthday of operation . The turbine is actually almost nine years old . Out of Warranty
When the operation and maintenance issues become million dollar repairs in the next few years who will take the blame for a financial failure ?
D. I. Vided
12:09 pm on Thursday, January 24, 2013
I am a resident of Falmouth and I don't think it matters where in town I live. I think there's something pathetically wrong with our town when neighbors turn their backs on neighbors. I read Tulinski's comment and think.. he seems the neighbor that, after hearing shots being fired and someone screening for help, or smelling smoke waffle into his bedroom from the house ablaze next door - would only shut his window. This town has turned VERY COLD. I'm ashamed
Julie Cunningham Goulart
4:45 pm on Thursday, January 24, 2013
you took the words right out of my mouth!
Bill Carson
12:11 pm on Thursday, January 24, 2013
Princeton ,Massachusetts pays the highest electric rates in Massachusetts because of the failure of its 1.5 Megawatt three year old wind turbine. The Town of Falmouth is only about six months behind Princeton . It is true they provide clean energy but at a cost of health of the residents of Falmouth and soon the expense of the entire town.
These are commercial megawatt turbines placed in residential locations .I understand the people who don't live near the turbines only care about money and not your neighbors health . You need to look at the future and the cost associated with a small town operation of a turbine !
http://www.windaction.org/documents/36015
Princeton Municipal Light Department's (PMLD) admits wind turbine failure
D. I. Vided
12:33 pm on Thursday, January 24, 2013
Mr. Carson - I don't know how to judge your comparison between two different makers and models of turbines. I have been told that I'm a decent judge of character. Good character was on display by the selectmen at the public hearing. The character of decision makers are most valued when they ask
what “the People” think. I would urge decision maker and citizens, embrace the character of being neighborly. The problem seems not about
whether you’re for or against wind energy. The problem is about the character of our community. It's sad day when Falmouth neighbors cease to care for the welfare of each other. We can't afford the damage of community character that would cost.
sue hobart
12:35 pm on Thursday, January 24, 2013
Tulinskis comment goes to the true root of the problem. If it doesn't bother ME it's not a problem. Most Falmouth residents are not bothered at all.
But what about me and the home I designed built loved and have been forced to abandon for the sake of my health? What about lives that are being shortened by the hour and the devastation of the few. If I was your MOTHER would you care then?
We have lost our community indeed with people like this at the wheel and making up the quiet and unrepentant majority.
This is why no matter what happens I will not be able to return in good faith to Falmouth.
The world is changing too fast and NOT for the better. It's every man for himself now I guess. It's just been such a bitter awakening because that's not how I have behaved over the years and it's a sad conclusion to accept after living a life where I believed in peoples overall goodness and trusted, obviously way too much.
Many did in fact come forth in support of the turbine victims last night and I am grateful for their efforts. Unfortunately I am still concerned that they, like me, are just beginning to see the harsh new reality and hoping to make a last stand against this selfish thinking and hoping to makes a difference.
Personally I fear it is too late for Falmouth and I'm not holding my breath anymore. So I will pray for a miracle but expect this loss of caring to proliferate. It's sad and inevitable.
Bill Carson
1:31 pm on Thursday, January 24, 2013
Sue , Don't worry these turbines break down in a short period of time ,Falmouth Wind 1 is just starting to break down with the condensation on that electric switch at Thanksgiving . That's just the start of the problems . This turbine has been a curse on the town since they bought it with a 1 million dollar advance of Renewable Energy Credits from the state ! What a deal NOT !
Vestas Wind Systems of Denmark has purchased other wind companies like NEG Micron and Nordtank Energy Group in the early 2000s. Vestas recently has admitted issues with 376 of its V90 3MW gearboxes.
The gear box issues continue today. The Otis AFB ,Cape Cod says their three year old Furlander 1.5 MW turbine has no problems .The air base is in denial of how much the gear box is going to cost to replace.
One company made many of the same gear box units for all the wind turbine manufacturers .
The Falmouth Town Meeting Members are only being told the good news about the older commercial wind turbines that were sold to last twenty or thirty years - The truth is three to five years before mega operation and maintenance issues - small towns can't afford a catastrophic gear box failure.
D. I. Vided
7:12 pm on Thursday, January 24, 2013
Sue - I plan to watch the playback of the meeting but my first impression from newspaper and online reports is that clearly, a mandate to effect a sense of priority to selectmen was attempted. One "value," so crucial to our community's integrity that, without its resolution being accomplished first, compromises Falmouth's fundamental principles of ethics. I still have faith in the good neighbors of Falmouth!
Bill Carson
1:32 pm on Thursday, January 24, 2013
The turbine is cursed : Sue , Don't worry these turbines break down in a short period of time ,Falmouth Wind 1 is just starting to break down with the condensation on that electric switch at Thanksgiving . That's just the start of the problems . This turbine has been a curse on the town since they bought it with a 1 million dollar advance of Renewable Energy Credits from the state ! What a deal NOT !
Vestas Wind Systems of Denmark has purchased other wind companies like NEG Micron and Nordtank Energy Group in the early 2000s. Vestas recently has admitted issues with 376 of its V90 3MW gearboxes.
The gear box issues continue today. The Otis AFB ,Cape Cod says their three year old Furlander 1.5 MW turbine has no problems .The air base is in denial of how much the gear box is going to cost to replace.
One company made many of the same gear box units for all the wind turbine manufacturers .
The Falmouth Town Meeting Members are only being told the good news about the older commercial wind turbines that were sold to last twenty or thirty years - The truth is three to five years before mega operation and maintenance issues - small towns can't afford a catastrophic gear box failure.
Falmouth-Resident
1:54 pm on Thursday, January 24, 2013
I am a resident and I vote.... TAKE THEM DOWN PLEASE
Bill Carson
2:50 pm on Thursday, January 24, 2013
Several years back, we wrote how the Massachusetts Technology Collaborative (MTC), a quasi-public agency tasked with encouraging renewable energy technologies in the State of Massachusetts, gambled $5.28 million in public funds to purchase two new (at the time) Vestes V82 – 1.65 megawatt wind turbines. MTC hoped to jumpstart local public renewable projects by making the Vestas turbines available for sale.
The Town of Orleans was one of the first candidates for the towers but sensitive watershed areas compromised the plan. The agency then moved aggressively to place them in Mattapoisett, MA and neighboring Fairhaven, MA, but public opposition to the giant turbines too close to residential areas stymied the effort. MTC took delivery of the V82 turbines in September, 2006 and warehoused them in Houston, TX at storage fees as high as $3,000 a month. They eventually found a 'home' -- in Falmouth, MA.
WIND 1 went online in early 2010 at Falmouth’s Wastewater Treatment Plant. WIND 2, currently under construction, will be located only 1000 feet (less than five rotor widths) away.
With homes a short 1,350 feet from WIND 1, as soon as it started spinning complaints about noise and shadow flicker hit the media.
Bill Carson
2:54 pm on Thursday, January 24, 2013
GE and Buy America
While WIND 1 was community funded through a combination of general bonds, grants and advanced payments on renewable energy credits sold under the State's Renewable Portfolio Standard program, the second is being funded entirely through the American Recovery and Reinvestment Act of 2009 (ARRA) .
Recall, ARRA Section 1605 asserts a "buy America" provision and MTC's Vestas V82 (vintage 2005-06) turbines were not American-made. Falmouth needed a waiver to get its hands on the stimulus money or change out MTC's turbine in-hand for a domestic-made equivalent.
Apparently, the Town solicited General Electric as a potential turbine supplier, but GE's siting standards required a safety setback of 1.5 times the hub height plus rotor diameter be maintained in the event of icing. The setback distance would be measured from occupied structures, roads, property lines and public access areas.
Unless the turbine was moved, GE was unwilling to do business.
Bill Carson
2:56 pm on Thursday, January 24, 2013
Waiver granted
The federal government, in this case the EPA, determined that no domestic manufactured wind turbines were available that could meet WIND 2's project design and performance specifications. The waiver was granted.
The notice of waiver that appeared in the Federal Register on April 27, 2010 included this text:
Section 1605 of the ARRA requires that none of the appropriated funds may be used for the construction, alteration, maintenance, or repair of a public building or a public works project unless all of the iron, steel, and manufactured goods used in the project is produced in the United States, So, let's be clear here. GE, which has more of its turbines installed in the United States than any other manufacturer, and arguably the most experience with operating turbines in the varied climates within the US -- certainly more experience than EPA and the Town of Falmouth -- raised public safety concerns over the risks of ice throw, and Falmouth looked the other way. EPA, in turn, agreed that applying GE safety standards to the site would be "inconsistent with the public interest". Is it any wonder Falmouth is the latest poster child for poor turbine siting?
Bill Carson
2:57 pm on Thursday, January 24, 2013
The risk is real
If anyone doubts that ice builds up on turbines in the Massachusetts area, it's worth watching this short video clip from Newburyport, MA where a smaller 600-kw turbine standing just under 300-feet was erected. Or watch this clip from Wisconsin involving turbines similar in size to the V82.
The story doesn't end there.
Two months prior to Falmouth receiving its waiver, EPA supported a waiver request by the Massachusetts Water Resources Authority (“MWRA”) to acquire a turbine built by Chinese turbine maker, Sinovel. The turbine is expected to power the DeLauri Pump Station in Charlestown, Massachusetts where GE found the setback distances insufficient to protect the public from ice throw. Lucky for the MWRA, Sinovel was more than happy to take the money.
Falmouth Neighbor
3:34 pm on Thursday, January 24, 2013
Last nights meeting was courteous and friendly. There was a mix of residents in the audience in which 43 people spoke. And yes most of those indicated that the turbines should be removed or curtailed. And 4 of those were from out of town (and outspoken wind opponents in every town where there is a wind turbine).
There were noticeable faces and some new voices. The thing I found very interesting is that not one person asked a question about the options or the report or how taking the turbines down might affect fiscal concerns (don't infer that I am putting finance over health, but it is important to understand the economics). If you support taking the turbines down, then provide a way to minimize the fiscal impact on the whole town. And asking the state for money is not the sole answer because if it were we wouldn't be here today having these discussions. It is easy to say take them down, and I am not totally against that, but I want a real answer to how the debt obligations will be paid. I don't have a lot of money and the tax rate just went up to $8.00 per $1000 from $6 and change. This will have an affect on my household income. And with new tax increases due to the fiscal cliff, I am looking at less money for my family this year than last year. And that money does provide for my family's health and welfare. Taking the turbines down and bearing that cost in my property taxes may cause me to have to leave Falmouth. It's an issue and a choice I will have to face.
Bill Carson
4:09 pm on Thursday, January 24, 2013
1st - You have to understand the turbines don't last twenty years - five years is a stretch . The tubines like in Princeton Mass are costing more than if they didn't have one.
2nd I have forwarded all the negative information to Vestas Wind Company . They approved it .They should pay .Here is the response that says they are working with the customer . The town is the customer : Dear Mr Carson, Thank you for your email to Vestas .We can inform you that Vestas has worked diligently with our customer on a solution so they can manage the turbines’ operating hours.
From: Vestas Press Centre (Mailbox) <pressoffice@vestas.com>
To: Bill Carson Sent: Thursday, January 10, 2013 7:18 AM
Subject: RE: Falmouth MA USA Vestas Noise Issues 2013
Yours sincerely Pressoffice Vestas Wind Systems A/S http://vestas.com/
Third and last the Massachusetts Technology Collaborative knew exactley what they were doing when they dumped the turbines on Falmouth . They should pay too.
The MTC now the Mass CEC is paying 100 million to build the New Bedford Marine Commerce Terminal - They have the money to pay back Falmouth
mark cool
7:29 pm on Thursday, January 24, 2013
Hey Neighbor - According to another local news outlet Falmouth has it's own "fiscal cliff." Town Manager Suso, in his proposed budget to the Finance Committee, spoke of FY 2014 (2015?) projections based upon a “sustainable model” involving 24/7 turbine operations. Mr. Suso’s budget proposal, given the “purchasing of home” contingency portion of one option, and the "break-even" fiscally static result of the other wind operational options, I wonder if our town manager has a pulse on what's happening? His proposal doesn't account or make contingencies for purchasing homes/ if turbines are operated 24/7. The "who'll pay for the debt obligation" question seemingly is being ignored by our town's top exec.
Falmouth Neighbor
4:36 pm on Thursday, January 24, 2013
Once again, you are not providing solutions to the debt obligation but who YOU THINK should pay for them. As you continually state in your various posts that Vestas and MTC (MassCEC) and the state are all responsible for where the turbines ended up, but Falmouth decided to buy the turbines and is the owner (regardless of the good or bad of the situation). The debt obligation belongs to the town of Falmouth and therefore the taxpayers. It is unlikely to think that Vestas, MTC (MassCEC) or the state is going to take ownership and just hand over the money; if it were there or they saw fault they could/would have done it by now.
The turbines have been operating for almost three years with intermittent down times for various reasons. The turbines function. Each one of those entities has a case to say that the debt belongs to Falmouth.
Now we need to hear reasonable and salient solutions to the debt obligation should the turbines be removed. And no, solar is not an option - it REQUIRES a $3M grant to install the array(s) and another $3.9M to be put into a stabilization type account to pay the turbine debt. If we could get $3.9M to put into an account, we could pay the debt and take down the turbines so NO that option does not relieve the debt obligation. It assumes that there is money available to install an array and not have it cost the taxpayers - UNLIKELY.
Are the complaining neighbors willing to take on the burden of the debt obligation since they want them gone?
Bill Carson
5:48 pm on Thursday, January 24, 2013
Once again its the money before the health of the neighbors. What price do you put on a human life ? The bottom line here is the residents of Falmouth got taken on the purchase of the turbine .Why didn't anyone in Falmouth question why it took almost ten years to sell these turbines ? What happened in Fairhaven, Dartmouth ,Mattapoisett and Marion why did those towns turn down the turbines ? Why couldn't the MTC sell the turbines at an auction ? Why did the MTC give the Town of Falmouth an advance of 1 million in RECs ,renewable energy credits ?
The town got taken they bought a Trojan Horse ! In the next year you'll understand the maintenance costs sky rocket .
Commercial wind turbine development is “mainstream news” .It is being exposed as just another massive political ponzi scheme in which local politicians are now being accused of criminal acts that affect humanity.
Instead of placing a complete moratorium on all commercial wind development at once until a complete public review is concluded, these local political committed tyrants are pushing ahead against all the negative tales flowing in hourly to newsrooms around the world.
mark cool
6:30 pm on Thursday, January 24, 2013
Hey Neighbor - I very much appreciate the point you've made, as well as your 'real' concern. Your livelihood and income relate directly to your family's well being. The debt obligation was assumed by the community (via town meeting). In effect, as soon as that petition passed - everyone in the community went "all-in". Here we are now, looking at a municipal capital project being a mistake. From the beginning , I suggested that the solution to the town's "all-in" capital investment had to be another "all-in" capital bailout. Sure the state will do something to soften the blow, whether it be for the appearance of maintaining 'party solidarity', taking responsibility for bad advise or whatever... Yet Falmouth is the primary owner of the debt. We went 'all-in' when we expected (and were told) this was a WINDFALL Unfortunately, we now know better. And yes, I know for a fact complaining neighbors WILL take on the burden of debt obligation... we're all equal partners in our community ~ We're "all-in" for the problem being solved. Health has no price tag. This mistake does & I'm willing to pay.
Falmouth Neighbor
8:51 pm on Thursday, January 24, 2013
Mr. Cool (that sounds funny) - the debt obligation is a function of the operation of the turbines not a tax on the taxpayers. TM voted the funds PROVIDED they were repaid through turbine revenue and from what I have read, they do produce revenue (when fully operating). Now I'm not saying they can't come down, but how will the debt obligation be repaid? In the short time frame before TM this year, the selectmen need a specific answer to that question. And that is what TM members will be asking as well. It's not that anyone is really against the neighbors, I don't believe that. It's that there are other real questions and issues, too.
Julie Cunningham Goulart
4:44 pm on Thursday, January 24, 2013
How could we ever turn our backs on our neighbors....how sad! This is why i LOVE living in Mashpee....Mashpee Town Hall and all its people are some of the best people i ever met-No Good Old Boy's club here....
Sue....you and all the others who have fallen victim to the wind turbines my heart goes out to you-I am all for clean energy but NEVER at the health of my neighbors!
mark cool
6:08 pm on Thursday, January 24, 2013
Falmouth Son, State Representative David T. Vieira has made our community proud. Great moments are born from great opportunity ~ Mr. Vieira, by this courageous Act, has seized both.
The Commonwealth of Massachusetts
_________________
PRESENTED BY:
David T. Vieira
_______________
To the Honorable Senate and House of Representatives of the Commonwealth of Massachusetts in General Court assembled:
The undersigned legislators and/or citizens respectfully petition for the passage of the accompanying bill:
**"An Act relieving the adverse effects of wind energy"**
sue hobart
6:33 pm on Thursday, January 24, 2013
God bless David Viera... sign me up. I have already lost so much . And Bill , thanks for attempting to comfort me but unfortunately My bane is the NOT US webb turbine and the town will never deal with it.
So I get to sue WEBB and TELEDYNE ... a mutli million corporation with big lawyers and bank accounts. Not sure I can gamble with what little money we have left after leaving our home.
I do wonder what might have happened if 2 of the dangerous turbines were NOT owned by the town.... would they have still let the harm continue.
heartless corporations, heartless town managers and damaged lives...Until we call this behavior out and give victims a way to defend themselves everybody better keep their eyes wide open .
Bill Carson
7:48 pm on Thursday, January 24, 2013
Sue , It won't be that long before the operation and maintenance shuts down the turbines anyway . I don't understand why the town didn't have the maintenance contractor give the CBI and the Town Meeting Members a report on the expected maintenance of the turbines in the next year and what to expect from them .
Many turbines have broken down big time in the last year that are only three years old . A small town can't buy and afford to run a couple of turbines it's not economically feasable .
Bill Carson
9:12 pm on Thursday, January 24, 2013
Falmouth Neighbor,You don't get it ! The wind turbines are failing at three years. Portsmouth High School ,Rhode Island -Otis ANG Base Cape Cod .
Here is the story from Princeton Ma - How long before the Famouth Wind Turbines Fail ?
Princeton Municipal Light Department's admits wind facility is losing money, raising rates
September 12, 2012 by Brian Allen, General Manager of PMLD
Summary:
This letter written by Princeton Municipal Light Department's (PMLD) General Manager, Brian Allen, offers a candid assessment of the utility's two-turbine (3.0 MW) project. The turbines have failed to live up to expected production levels. The project has also been plagued by technical problems. Rather than reducing rates for customers, the project lost $1.875 million and will continue to lose $600,000 yearly under current circumstances. Excerpts of the letter are provided below. The full letter can be read by clicking on the link at the bottom of this page.
http://www.windaction.org/documents/36015
Falmouth Neighbor
9:40 pm on Thursday, January 24, 2013
Mr. Carson, I am not making any reference to turbine lifespan or operation so I don't understand what you mean when saying "I don't get it". You mean that because some wind turbine manufacturer's have had failures then all wind turbines will have failures? I do not agree. There are as many cases for properly functioning turbines as their are problematic ones.
My sole question in this issue about removing the turbines, should that be the decision brought to town meeting, is how the debt obligation will be paid. Board of Selectmen MUST have this answer and it must be specific. But I don't think it should be borne on the entire town because that is not what was voted on by the town for the installation and operation of turbines.
I am not disputing or supporting anyone's position about their usefulness, their sound impact or possible health issues. But I want to know where $4M+ is going to come from to relieve the debt obligation should they not operate as originally planned.
Bill Carson
9:18 pm on Thursday, January 24, 2013
One million in repairs to Portsmouth RI wind turbine three years old .
FINANCIAL CONSIDERATIONS
In order to determine the profitability of continued turbine operation subsequent to a gearbox replacement, two scenarios are considered, a three-year and a ten-year gearbox life.
http://www.portsmouthri.com/documents/Turbine_Gearbox.pdf
Bill Carson
9:22 pm on Thursday, January 24, 2013
Military Base Having Trouble With German-Made Wind Turbine
By: Diana T. Barth
Published: 01/17/13
"Performance of that machine was impacted by lower-than-average wind speeds, a number of mechanical problems, and poor service by the manufacturer, they said.
Those issues included worn generator brushes and loss of charging capacity in backup systems.
A wind turbine’s “yaw drive” orients the motor housing of a turbine to the wind, and a major component of that drive is a gearbox. Diagnostic evidence suggests that the German gearbox may be failing due to a bad bearing and, possibly, because of poor design, the AFCEC reported:
http://www.capenews.net/communities/bourne/news/2333
mark cool
9:42 pm on Thursday, January 24, 2013
Hey Neighbor - you're absolutely correct about the debt repayment from turbine production receipts. However, full operation 24/7 will be impossible due to night noise exceedances measured by the DEP on wind 1 & even more impacting when wind2 runs simultaneously. (unfortunately they weren't tested together. The financial projections from the WTOP, clearly indicate (with night curtailment allowing for a healthy period of sleep) that this protocol is unsustainable, in terms of budget. The long and short of it.. Answering your question - the tax payer will pay the debt service by either bleeding a slow fiscal death or by amputating and cutting off the likely more protracted losses. In either case, the fiscal burden will be shared by all taxpayers. Taking them down allows the complaining neighbors to share equally in the burden. Running them with a nighttime curtailment extracts from these neighbors not only a shared fiscal debt, but also a health and well being toll.
Bill Carson
7:40 am on Friday, January 25, 2013
Health & Windfarms: Experimentation on people without their consent
In this video, Curt Devlin explains to windfarm neighbours how they are actually being used as guinea pigs without previous information and consent, which constitutes a clear violation of their Human Rights.
Recorded at the Falmouth Conference on Human Rights* - November 10, 2012 - Falmouth Public Library - Falmouth, MA, USA
* Science, medicine and engineering were called upon to explain the impacts of living too close to industrial wind turbines.
http://www.epaw.org/documents.php?lang=en&article=v4